Century was commissioned to undertake the emergency manufacture of 6 towers in 4 weeks, to replace collapsed towers. The project was completed in an incredibly tight timeframe, given the normal lead-time for a single tower is 8 weeks. As a result of processes developed specifically for the project, all 6 towers were delivered on schedule, arguably an industry best. Plus, the damaged transmission line was restored within the timeframe.
Critical Equipment Manufacture and Welding Sequence
Critical equipment fabrication requires a strong focus on welding techniques. It is important to ensure that proper welding techniques are employed to achieve high-quality and